Dongying Hebang Chemical Co., Ltd. 60000 Tons/Year Special Epoxy Resin Integration Project (Phase I) (Phase I) Completion Environmental Protection Acceptance Monitoring Report Publicized in Full

2026-02-24 Environmental Information

In accordance with the requirements of the "Regulations on the Administration of Environmental Protection of Construction Projects" (Order No. 682 of the State Council), "Interim Measures for the Acceptance of Environmental Protection for the Completion of Construction Projects" (2017 No. 4) and other documents, the "Dongying Hebang Chemical Co., Ltd. 60000 Tons/Year Special Epoxy Resin Integration Project (Phase I) (Phase I) Completion Environmental Protection Acceptance Monitoring Report" is announced as follows:

Construction unit: Dongying Hebang Chemical Co., Ltd.

Project Name: 60000 Tons/Year Special Epoxy Resin Integration Project (Phase I) (Phase I)

Construction site: to the west of Donggang Road, Dongying Port Chemical Industry Park, to the north of Gangbei Road, and in the existing factory area of Dongying Hebang Chemical Co., Ltd.

Contents of publicity: acceptance report and acceptance opinions (see annex for details)

Publicity Date: February 24, 2026-March 20, 2026 (20 working days)

during the

publicity period, the public can contact our unit by letter, call or other means to consult relevant information, and put forward relevant opinions and suggestions, reflect the problems and leave contact information, so that we can reply to feedback in time.

Contact: Li Qishuai

contact number: 0546-7710820

Email: hbhuanbao@hebangchenmical.com

Acceptance Team Conclusion: Through acceptance monitoring and on-site verification, the Project conforms to the national industrial policy and environmental protection policy. All pollutant emission concentrations of the project meet the requirements of the corresponding standards. The environmental protection procedures of this project are complete, the environmental protection requirements in the EIA approval are basically implemented, and the environmental protection acceptance conditions for the completion of the construction project are met. Waste gas, waste water and noise can be discharged up to standard, solid waste disposal is reasonable, and the project meets the completion acceptance conditions in terms of environmental protection. The acceptance team agrees that the project can pass the completion environmental protection acceptance.

Acceptance Monitoring Report and Opinion Publicity Link:

links: https://pan.baidu.com/s/18Il3TcnDlZfgLw6lzIkZsQ?pwd=zkqi

extraction code: zkqi

Dongying Hebang Chemical Co., Ltd

24 February 2026